How Do You Fill In the ESPD (European Single Procurement Document)?

The ESPD is a self-declaration. You state that you are not excluded and that you meet the selection criteria now, and prove it later.

TenderFaro Editorial TeamPublished 2026-11-25Updated 2026-11-2510 min read

Part of the guide to public tenders.

On this page

What is the ESPD?

The ESPD is a self-declaration. You state, in a standard EU form, that you are not excluded and that you meet the buyer's selection criteria. You do not attach the certificates yet. The buyer accepts your word as preliminary evidence, and asks for the proof later, at the latest from the bidder it intends to award the contract to. That makes the ESPD faster than collecting paper for every bid. It also makes it easy to get wrong, because nothing stops you from declaring something you cannot later prove.

The European Single Procurement Document was introduced by Article 59 of Directive 2014/24/EU. Under that article, buyers must accept the ESPD as preliminary evidence in place of certificates from public authorities or third parties. It covers three things: that no exclusion ground applies to you, that you meet the selection criteria, and, where the buyer limits the number of candidates, that you meet the rules for that.

The form follows a standard set by the European Commission and must be provided in electronic form. The buyer prepares an ESPD Request, which sets out what it wants to know. You answer with an ESPD Response. The Commission does not run an ESPD service of its own. EU countries provide national ESPD services or build the form into their procurement platforms, so the screen you see depends on where the tender is published. The structure underneath is the same.

When will you meet the ESPD?

You will usually meet the ESPD in procedures run under the EU procurement directives, which are the ones advertised on TED. Many countries use it below the EU thresholds too, but that is a national choice. The tender documents say whether an ESPD is required and how to submit it.

The ESPD is an EU instrument. UK procurements follow UK rules and forms, so check the tender pack rather than assuming the ESPD applies.

What to gather before you start

Gather what the form will ask for, so you are not hunting for it close to the deadline. If you keep this material in an evidence library, most of the form becomes copying rather than searching.

  • Company registration details, VAT number and contact person.
  • The names and roles of the people who can represent the company.
  • Whether you are a micro, small or medium-sized enterprise.
  • Turnover figures, insurance levels, certificates and project references that match the selection criteria in this tender.
  • The details of any partner, member of a group or subcontractor involved in the bid.

Part I: Information on the procedure

The buyer fills this in: the publication reference, who the buyer is, and the procedure. Your job is to check it. Make sure it matches the notice and the lot you are bidding for. A Response attached to the wrong lot is an avoidable problem.

Part II: Information about your company

This is where you describe yourself. Sections C and D matter most for SMEs. If you rely on another company's capacity to meet a requirement, that company files its own ESPD, as the section on groups below explains.

  • A. Information about the economic operator: your identification details, your size, whether you are on an official list of approved operators or hold an equivalent certificate, and whether you are bidding together with others.
  • B. Representatives: the people authorised to represent you for this procedure.
  • C. Reliance on the capacities of other entities: whether you rely on another company to meet a selection criterion.
  • D. Subcontractors you do not rely on: information about subcontracting where you are not relying on the subcontractor's capacity, if the buyer asks for it.

Part III: Exclusion grounds

Part III asks whether any reason to exclude you applies. Answer every question the buyer included. If a ground does apply, the form lets you describe the measures you have taken to show you are reliable again, often called self-cleaning. Do not leave the answer blank or guess: check with whoever handles your company's legal and tax matters.

  • A. Criminal convictions, such as participation in a criminal organisation, corruption, fraud, terrorist offences, money laundering, and child labour or human trafficking.
  • B. Payment of taxes or social security contributions.
  • C. Insolvency, conflicts of interest and professional misconduct, among other grounds the buyer may include.
  • D. Purely national exclusion grounds that the buyer's country adds.

Part IV: Selection criteria

Part IV is where you declare that you meet the buyer's minimum requirements. Depending on the buyer's choice, you either give a single global indication that you meet all of them, or answer each section. Only the criteria the buyer selected will appear.

Whatever you declare here should match the evidence you can produce later, figure for figure. A turnover that differs from your accounts, or a reference with a different value than the one on your reference letter, invites questions.

  • A. Suitability, such as registration in a professional or trade register.
  • B. Economic and financial standing, such as turnover and insurance.
  • C. Technical and professional ability, such as references, staff and equipment.
  • D. Quality assurance and environmental management, such as certificates to recognised standards.

Parts V and VI: Reducing candidates and concluding statements

Part V only applies when the buyer limits how many qualified candidates it will invite, as in restricted procedures, and has published objective criteria for choosing them. If it applies, you show how you meet those criteria. If it does not, it will not appear or can be left as it is.

In Part VI you confirm that the information is accurate, that you can provide the supporting documents without delay when asked, and you consent to the buyer accessing them where they are available. You add the date, the place and the signature, in the way the platform or national rules require.

Who files an ESPD in a group bid?

The ESPD is filed by every party the buyer needs to assess, not just the lead bidder. Missing a partner's ESPD is a common way for a group bid to run into trouble. Agree early who prepares each one and who checks them. Our post on how SMEs can bid with a partner covers the choice between a consortium, reliance and subcontracting in more depth.

  • In a group or consortium, each member completes its own ESPD Response for each lot. The group leader gathers them and submits them with the bid.
  • A company whose capacity you rely on to meet a selection criterion also completes a separate ESPD Response.
  • Subcontractors you do not rely on only need to be described if the buyer asks.

What happens after you submit

The ESPD postpones the paperwork. It does not remove it. This is why the ESPD belongs in your bid/no-bid scoring: if you cannot produce the proof quickly, you should know that before you declare it. Expired evidence is also one of the mistakes that disqualify bids.

  • The buyer can ask any bidder for all or part of the supporting documents at any point in the procedure, if it is needed for the procedure to run properly.
  • Before awarding the contract, the buyer asks the bidder it intends to award to for up-to-date supporting documents, with some exceptions for contracts based on framework agreements.
  • You do not have to submit documents that the buyer can get free of charge from a national database, or that it already holds.

Can you reuse an ESPD?

Yes. Article 59 allows you to reuse an ESPD from an earlier procedure, as long as you confirm the information is still correct. Most ESPD services let you save a Response and import it into the next one.

Keep a master version and review it before each bid. Dates move, certificates expire, representatives change and turnover figures roll into a new year. A reused ESPD that has gone stale is worse than a new one.

ESPD mistakes to avoid

Most ESPD problems are not about the law. They are about care.

  • Declaring what you cannot prove: every "yes" may have to be backed by a document before award.
  • Forgetting the other parties: each group member and each company you rely on needs its own Response.
  • Answering the wrong lot: check Part I against the lot you are bidding for.
  • Numbers that do not match: use the same turnover, insurance and reference figures in the ESPD and in your evidence.
  • Reusing without reviewing: update representatives, dates and figures every time.

How TenderFaro helps with this

TenderFaro does not fill in or sign your ESPD; that stays with your team. It helps with the work around it. It extracts the selection criteria and deadlines from the tender documents with a link to each source passage, and its evidence matching compares them with the certificates, insurance, references and policies in your company profile. Gaps show up before you declare anything, which is the point of a careful tender qualification.

This article explains the general EU framework. National rules, procurement platforms and individual tender documents can add requirements. It is not legal advice.

Frequently asked questions

What is the ESPD?

The European Single Procurement Document is a standard self-declaration used in EU public procurement. Bidders use it to state that no exclusion ground applies and that they meet the selection criteria, in place of submitting certificates up front.

Is the ESPD mandatory?

Under Article 59 of Directive 2014/24/EU, buyers must accept the ESPD as preliminary evidence in procedures covered by the directive. Whether you must submit one, and how, is set out in each tender's documents and in national rules.

Does every member of a consortium need an ESPD?

Yes. Each member of a group completes its own ESPD Response for each lot, and so does any company whose capacity you rely on to meet a selection criterion.

What is the difference between an ESPD Request and an ESPD Response?

The Request is prepared by the buyer and sets out what it wants to know. The Response is what you, the bidder, complete and submit.

When do I have to provide the certificates?

When the buyer asks for them, which can be at any point in the procedure. At the latest, the bidder the buyer intends to award the contract to must provide up-to-date supporting documents before the award, with limited exceptions.

Is the ESPD used in the UK?

The ESPD is an EU instrument. UK procurements follow UK law and their own forms, so check the tender documents for what is required.

Sources and methodology

This article draws on public procurement guidance and TenderFaro product research. It does not provide legal advice or determine tender eligibility.

Make the evidence behind a bid decision easier to review.

TenderFaro structures requirements, connects company evidence and preserves citations so teams can review the same facts before they decide.

Explore a sample analysis →

Continue reading

Editorial updates are on the way.

We are preparing a practical TenderFaro Journal newsletter. Subscription is not enabled yet, so this page never collects or stores your email address.